Customer: LLP “Kazakhstan Wagon Building Company”
Design capacity: 2,000 open-top wagons per year.

Techvagonmash has implemented a comprehensive project for the establishment of a modern freight railway wagon manufacturing facility based at the enterprise Kazakhstan Wagon Building Company in the city of Ekibastuz.
The project was aimed at creating a full production cycle — from infrastructure preparation and implementation of technological processes to the launch of serial production of freight wagons that meet the requirements of railway administrations and international quality standards.


Key project objectives
- technical consulting and training of the Customer’s personnel;
- development of the technological concept of wagon manufacturing;
- design of production flows and equipment layout;
- selection, supply, and implementation of specialized technological equipment;
- development and adaptation of design and process documentation;
- support of commissioning activities and production start-up;


Role of Techvagonmash
Within the framework of the project, Techvagonmash acted as the general technological partner, providing:
- system engineering of the wagon manufacturing facility;
- integration of equipment into a unified production complex;
- transfer of competencies and practical experience in serial wagon manufacturing;
- project support at all stages — from concept to reaching design capacity.